The following corrections may please be made to the Tender Documents: Para 1.1 of Part I: General Terms may be read as follows:

Background

Kochi Metro Rail Ltd., represented by its Director Projects (the KMRL) intends to engage consultants for carrying out the “Environmental Impact Assessment” (EIA) study and ‘Environment Mitigation/Monitoring Plan’ for the Kochi Metro project. The consultant is to carry out the study on the Environmental Impact due to the project, recommend monitoring cum mitigating measures which are to be put in place and assist KMRL in EIA specific queries from the funding agencies.

Para 2.1 of Part II: Scope of Services may be read as follows:

The Employer shall retain 5% from each payment due to the Contractor till the completion of the Works. Upon the issue of a Certificate of Completion of the Works by the Director (Projects), the total amount retained shall be repaid to the Contractor. The Contractor may also exercise the option of substituting the retention money with an “on demand” Bank Guarantee.

Para 2.4.1.1 of Part II: Scope of Services may be read as follows: 2.4.1.1 Study of DPR for Metro Rail Corridor from Aluva to Petta;

Para 2.9.1 of Part II: Scope of Services may be read as follows:

2.9.1 The Total fees for the preparation of EIA Report will be as per the financial bid quoted by agency in INR plus Service Tax as applicable.

 